‘An extraordinary and extreme backstop’: Earthjustice warns Army off bypassing paused Iowa permit

Thien Chau, a senior attorney at Earthjustice, which represents the groups, called the emergency provision “an extraordinary and extreme backstop” and said the groups “strongly urge” the Army not to rely on it.

✦ Extractive summary — built from the sources' own reporting•From 1 source•2 min read•Updated November 21, 2026, 3:16 PM UTC
Key points
  • Acting Army Secretary Adam Telle said Monday was the “latest possible moment prior to a forecasted temperature drop, which would risk further destabilization of the material.” The 68 drums of lead azide, an explosive used to set off munitions, were stored on site for more than 20 years in a bath of ethanol and water.
  • The permit required the Army to model the plume using conservative assumptions so as not to “under-predict” potential impacts, and it states that EPA and Army experts agree the modeling is “not necessarily representative of actual conditions.” The Army held a public open house about the planned detonation in mid-October.
  • 13 after finding the material posed an “imminent and substantial endangerment to human health and the environment.” The pause lasts until the court rules on the groups’ emergency motion, which asks it to keep the permit on hold while it decides the case.

The council and the Sierra Club Iowa Chapter argue that the permit lacks adequate protections for health and the environment, that the EPA did not fully consider alternatives, and that it was issued without the public notice and comment they say the rules require.

Additional details
  • 16, and when it contacted state and local officials, “We were telling them for the first time.” Reynolds’ office has said neither the governor nor any state agency was told of the plans before the Army’s Nov.
  • Court of Appeals for the Eighth Circuit issued its order late Thursday, pausing the permit the EPA issued to the Army on Nov.
  • The standoff leaves residents of southeastern Iowa and western Illinois facing a weekend of uncertainty over whether a plume of lead-laden dust will drift across their towns and farmland on Monday.
  • 15, five days before the original blast date, it released the detonation date and plume maps, meeting the permit’s requirement to publish a preliminary forecast at least five days in advance.
  • Cody Smith, director of climate initiatives at the Iowa Environmental Council, one of the groups that filed the lawsuit, said detonating without the court’s approval would be unlawful.