AI & Tech

America's hyperscale bit barns draw as much power as entire states

The researchers acknowledge limitations, including that there wasn't enough available data to study all hyperscale sites in the US, and that the data did not allow them to differentiate between power used for general-purpose compute versus AI-specialized operations at individual campuses.

✦ Extractive summary — built from the sources' own reporting•From 1 source•1 min read•Updated November 17, 2026, 6:29 PM UTC
Key points
  • That means the electricity use and carbon footprint we're reporting could already be substantially larger now in 2026." Harvard's report also considers the mix of fuels being used to generate the electricity that powers all those hyperscale data houses.
  • Just 403 hyperscale datacenters consumed an estimated 1.8 percent of US electricity in 2024-25, and their carbon dioxide emissions were roughly two to three times an earlier forecast for 2018.
  • Across four operating scenarios, ranging from low-intensity use to AI-heavy workloads, electricity draw was believed to total 68-99 terawatt-hours (TWh).

Chan School of Public Health and the Harvard Data Science Initiative looked specifically at hyperscale facilities, the largest class of server farms that typically support cloud computing and AI processing.

Additional details
  • The researchers identified 403 hyperscale facilities by using a larger datacenter dataset, satellite imagery, and building footprints on OpenStreetMap.
  • The mix varies considerably between regional grids, so where a hyperscale facility is built makes a substantial difference to its attributed emissions.
  • "What we're seeing is already striking, but it's only a snapshot of a rapidly expanding industry," said Gianluca Guidi, lead author on the paper and postdoctoral fellow in the Department of Biostatistics at Harvard.
  • Rather than reading electricity meters, the researchers worked out consumption from each site's electrical capacity, the hours in a year, and assumptions about how heavily the facility was running.
  • The researchers also calculated carbon dioxide (CO2) emissions using eGRID2023 plant-level generation and emissions data from the US Environmental Protection Agency (EPA).

How this summary was made: extractive summary — built from the sources' own reporting. It is drawn only from the reporting of the sources listed below — read the originals for full detail. How we summarize →